LAMOILLE COUNTY TRANSMISSION UPGRADE PROJECT

Information Resources

VERMONT DEPARTMENT OF PUBLIC SERVICE

CONCLUSIONS & SUMMARIES
Direct Testimony
VT Department of Public Service &
VT Department of Health

Submitted to the Public Service Board on April 11, 2005

Overview
The Vermont Department of Public Service (DPS) testimony in the direct phase of Docket 7032 recommends that the Lamoille Transmission Upgrade Project (LTUP), referred to in the DPS testimony as the Lamoille County Project, be approved by the Public Service Board (PSB) with some modifications to address aesthetic concerns.

The DPS testifies that the project is needed both to improve reliability of the existing electrical network and to permit economic growth in and around the region for which the project is being designed.

DPS concludes that the project meets the criteria for the Board to grant a Certificate of Public Good under Title 30 Vermont Statutes Section 248 once appropriate modifications have been made to the project.

The DPS concludes that the project will have an adverse impact on aesthetics that is undue in some locations and that mitigation measures will be needed.

However, it concludes that there are no compelling health concerns requiring modification of the proposal.

Therefore, the DPS recommends that the PSB issue a Certificate of Public Good with recommended changes as specified in the DPS testimony.

Below are the DPS’s conclusions by topic followed by a summary of each witnesses’ testimony.

DPS Conclusions by Topic

Load Forecast/System Adequacy: DPS witness J. Riley Allen concludes that the proposed project is needed to support project load growth.

The petitioners provide a forecast of coincident peak load for the area covered by the project, the Lamoille County Study Area (LCSA), that shows growth from a current peak of roughly 74 MW (in the winter of 2004/05), to one that is about 19 MW higher in the next 10 years (in the winter of 2014/15).

While DPS has some concerns with the forecast methods employed by VELCO and believes that there are opportunities for controlling the load growth, DPS concludes that a transmission solution is needed even at existing loads, and that the forecasted loads are not unreasonable. The LCSA region is experiencing significant growth at this time and warrants immediate attention. The forecasts presented are not unreasonable when informed by recent patterns of growth, current plans for development in the Stowe community and the LCSA region, and generally the longer-term patterns of development in Stowe and Vermont generally. [full testimony] [summary of testimony]

Economic Benefit: DPS witnesses Sean Foley and George Smith conclude that the project will provide economic benefits to the State of Vermont. The primary benefit of the project to Vermont is in improving network reliability and permitting growth in and around the region for which the project is being designed.

The DPS reviewed a number of economic impacts related to the project, including the overall rate impacts, a major project in Stowe that will depend on the electricity, impacts on property values, tax collection, and the costs and impacts of unreliable transmission system services. The DPS concludes that the LTUP will provide an economic benefit to the state. [full testimony] [summary of testimony]

Technical Merit, Stability and Reliability, Cost: DPS witness George E. Smith considered the need for the proposed project in relation to least-cost criteria and system stability and reliability. With respect to the issue of reliability, the DPS recommends that the LCSA transmission and sub-transmission network be maintained at levels that assure reliable service to all customers supplied by the area sub-transmission system for loss of any single transmission line section or for a loss of a primary supply source to the area.

The DPS reviewed the proposed 115 kV transmission system upgrade from the standpoint of industry best practices and concludes the proposed solution meets the needs—well into the future—for “all-lines-in” service and that the proposed solution provides reliable service, under first-contingency conditions, for load levels of up to 98 MW.

DPS also concludes that the project meets the standards of least-cost once appropriate modifications have been made. DPS proposes alternative structures for a portion of the project. [full testimony] [summary of testimony]

Aesthetic and Related Impacts: DPS witness David Raphael concludes that the LTUP, as proposed by VELCO and the petitioners, will have an adverse impact on aesthetics that is undue in some locations.

For each such location, mitigation measures are recommended and, with such mitigation measures implemented, it can be concluded that the LTUP’s effect on aesthetics will not be unduly adverse. For example, DPS believes single pole structures are feasible and desirable for portions of the 115kV and 34.5kV circuits north of the Blush Hill tap.

The DPS supports Mr. Raphael’s recommendations in all but one area. Mr. Raphael concludes that overhead lines crossing the Waterbury Reservoir as proposed will not only be adverse, but unduly adverse. Mr. Raphael proposes undergrounding of the line instead which would add an extraordinary cost in proportion to the project and may present an unreasonable burden on ratepayers. For this reason DPS does not advocate for the burial of the lines at the reservoir. [full testimony] [summary of testimony]

Demand-Side Management (DSM) and Cost-Effective Alternatives: DPS witness Carole Welch concludes that while DSM opportunities could have been more vigorously pursued as an alternative to the project, DSM does not provide an adequate alternative to the proposed transmission project.

DPS concludes that other alternatives such as rate design, curtailment arrangements, and distributed generation have not been adequately explored to their full potential in the region. Nevertheless, such opportunities are likely to have small impacts in relation to the patterns of growth and therefore are not likely to alter the conclusion that the proposed project is needed. [full testimony] [summary of testimony]

Electric and Magnetic Fields (EMF): Carla A. White and Lawrence Crist from the Vermont Department of Health testify on behalf of the DPS that there are not compelling health reasons requiring modifications to the Lamoille Project related to the concerns over EMF emissions. Ms. White and Mr. Crist address concerns with the potential implications on health from elevated levels of electric and magnetic power frequency field exposure that would result from the VELCO proposal. [full testimony] [summary of testimony]

DOCKET 7032
CASE SCHEDULE

02.09.05
Public hearing

02.18.05
Deadline for intervention requests

03.10.05
Site visit

03.18.05
Last date for filing discovery requests on petitioners

03.28.05
Last date for petitioners’ prefiled direct testimony and exhibits

04.11.05
All parties other than petitioners prefile direct testimony and exhibits

05.02.05
Last day to serve discovery on April 11 prefiled testimony and exhibits

05.12.05
Last day for discovery responses

05.23.05
All parties prefile rebuttal testimony and exhibits

06.03.05
Last day to serve discovery on rebuttal prefiled testimony and exhibits

06.13.05
Last day for responses to rebuttal discovery

06.27.05
All parties prefile surrebuttal testimony and exhibits

07.06.05
Technical hearing

07.07.05
Technical hearing

07.08.05
Technical hearing

07.18.05 (week of)
Technical hearings

08.08.05
Briefs due

08.22.05
Reply briefs due

10.19.05
Proposal for decision issued

11.04.05
Comments due on proposal for decision

12.07.05
Oral argument on proposal for decision


BOARD SCHEDULING ORDER (PDF)

SCHEDULE CHANGE MEMO OF 04.14.05 (PDF)