LAMOILLE COUNTY TRANSMISSION UPGRADE PROJECT

Information Resources

VERMONT DEPARTMENT OF PUBLIC SERVICE

Brief History of
Transmission Issues
in the Region

Introduction
T
he history of the Lamoille Transmission Upgrade Project dates back three decades.

In 1976, the Vermont Electric Power Company (VELCO), the utility that builds and operates transmission lines throughout the state, recommended that four utility companies serving Lamoille County build an emergency tie to strengthen the electrical grid network among themselves for increased reliability. VELCO warned at the time that this would only be a temporary fix, and that ultimately it would be necessary to bring in substantially more power into the region. Analysis at the time concluded that, while the emergency tie would delay the expenditure on a new 115 kV transmission line, such a line would eventually need to be constructed.

Load Growth
The emergency tie and other smaller temporary fixes were completed in the late 1970s. They helped to maintain reliability, but with continued development and demand on the system, its inadequacies again became apparent in 1986. At that time the Public Service Board (PSB), the quasi-judicial authority that regulates Vermont's utilities, ordered that Lamoille County utility companies convene to work out a solution to the problem. Numerous meetings were held among the utility companies serving the area, but no resolution was reached. The disagreements centered in large part on how the cost of the improvements would be divided up among the participating utilities, including Green Mountain Power, Morrisville Water and Light, Stowe Electric, and the Hardwick Electric Department.

Green Mountain Power, VELCO, and Central Vermont Public Service conducted further studies from 1987-1992. The conclusions from these studies all showed the need for system upgrades to maintain the reliability of the system. No action was taken until 1993 when Morrisville Water and Light filed an application to rebuild the power line that runs from Johnson to Morrisville. The Morrisville Water and Light project was completed in 1996 and was the last significant power line upgrade in the county.

Current Capacity
As a result of continued load growth, the subtransmission system that delivers power to utilities in the Lamoille County area is at its full capacity of 75 megawatts. At this level of demand, a single event such as a fallen power line or damage to a key piece of equipment could cause black outs. The proposed 115 kV line and associated equipment currently under consideration in Docket 7032 would increase the capacity of the area's subtransmission system by approximately 25 megawatts.

Proposed Build and Costs
In 2003, the Lamoille County utilities asked VELCO to develop a longer-term solution to the system limitations shortage. After studying a number of alternatives, VELCO proposed building a new 115 kV line from Duxbury to Stowe. Stowe Electric is paying for a large share of the construction costs and the costs of the approval process. The estimated $20 million costs for the project will be shared by other utilities in the region.

Note:The Department of Public Service thanks the Stowe Reporter for its contribution to this piece.

DOCKET 7032
CASE SCHEDULE

02.09.05
Public hearing

02.18.05
Deadline for intervention requests

03.10.05
Site visit

03.18.05
Last date for filing discovery requests on petitioners

03.28.05
Last date for petitioners’ prefiled direct testimony and exhibits

04.11.05
All parties other than petitioners prefile direct testimony and exhibits

05.02.05
Last day to serve discovery on April 11 prefiled testimony and exhibits

05.12.05
Last day for discovery responses

05.23.05
All parties prefile rebuttal testimony and exhibits

06.03.05
Last day to serve discovery on rebuttal prefiled testimony and exhibits

06.13.05
Last day for responses to rebuttal discovery

06.27.05
All parties prefile surrebuttal testimony and exhibits

07.06.05
Technical hearing

07.07.05
Technical hearing

07.08.05
Technical hearing

07.18.05 (week of)
Technical hearings

08.08.05
Briefs due

08.22.05
Reply briefs due

10.19.05
Proposal for decision issued

11.04.05
Comments due on proposal for decision

12.07.05
Oral argument on proposal for decision


BOARD SCHEDULING ORDER (PDF)

SCHEDULE CHANGE MEMO OF 04.14.05 (PDF)