LAMOILLE COUNTY TRANSMISSION UPGRADE PROJECT

Information Resources

VERMONT DEPARTMENT OF PUBLIC SERVICE

04.07.05
Town delays major power line review
BY SCOTT MONROE, STOWE REPORTER

Electric company officials who want to run new power lines on 58-foot-high structures through the southern portion of Stowe were told Monday that they needed to return in about a month to meet again with local planners and residents.

The proposed power line is part of a $13.4 million power upgrade for the region that has been requested by local electric utilities.

Residents at a Stowe Planning Commission meeting Monday said some neighbors to the proposed power line were not notified properly. Commission members felt that was enough to order Vermont Electric Power Company officials, who are required to notify townspeople, to return May 3 for another hearing.

VELCO needs Stowe municipal approval before it can file for state permits to build a 10.5-mile power line from Duxbury to a new substation in Stowe.

The 115 kilovolt transmission line would run from Duxbury along Route 2, and then along Route 100, through woods and farm fields, following an existing, smaller power line to the sub station off River Road. A bigger substation at the site also is planned. From Stowe, the new line would feed into the existing northern loop to supply both Lamoille County and Hardwick.

The power line crosses an estimated 59 private properties in Stowe, according to VELCO officials.

The bigger 115 kilovolt line has been requested by Stowe Electric to provide the region with enough electricity to handle growing power needs for at least the next 20 years.

The existing line feeding into the northern loop, which provides power to Stowe and neighboring communities, is currently fed by a much smaller 34.5 kilovolt line. Electric officials expect the new line to be operational by 2006.

VELCO officials estimate the power upgrade, which also includes the construction of two new substations, will cost $13.4 million. Approximately $3 million of that total is expected to be paid for by a New England utility pool; the remaining $10.4 million must be divided among a consortium of Lamoille County utilities.

Stowe, with the most growth in the county, will likely be paying the largest single chunk of the cost. Stowe Electric General Manager Bernard Machia at Monday’s meeting said Stowe would benefit the most and therefore pay the most.

“Stowe could be (paying) up to 40 percent of the project,” said Machia, who is the designated spokesperson for the electric consortium that includes Morrisville Water and Light, Hardwick Electric, Green Mountain Power and others. “Everybody’s meeting now to strike up cost sharing. We’re meeting again next week.”

Stowe Mountain Resort, which was expected to max out the northern loop’s current load capacity, is required to contribute $750,000 toward the power upgrade as part of its Act 250 permit. But the winter is generally not viewed as the season when most power is needed.

VELCO’s Project Manager Kim Moulton said the winter peak load of electricity has leveled recently, but the summer load has increased about 13 percent annually the last few years. This is attributed in part to more houses with more air-conditioners.

“The summer load scares me right now... more than the winter load,” Moulton said.

In order to handle future growth, especially during the upcoming summer months, the proposed upgrade is seen as essential by local electric utitilities.

“We feel now is the time to get this new additional source to the area,” Moulton said. “This is the least cost, best alternative we could develop.”

The new 115 Kilovolt line would use the same right of way as the old 34.5 Kilovolt line, which runs through mostly forest land west of Route 100, except where it crosses Moscow Road in Stowe. The line will be all above ground using “H-frame” poles, about 20 feet taller than the existing 38 foot-tall poles, and use a crosspiece to hold three lines.

The proposed upgrade comes in response to a 1999 VELCO study that found Lamoille County’s electrical infrastructure to be dangerously outdated. Without an upgrade homes and businesses will likely face blackouts and other diminished power problems, according to VELCO.

The local upgrade is part of a larger, statewide $200 million plan. The biggest power shortage is in Chittenden County, where the emergence of new stores and homes has stressed voltage load.

VELCO is required to meet with local planning commissions and townspeople before going ahead with such projects. Once it receives local approval, VELCO will seek Vermont Department of Public Service approval by the end of June 2004 and begin construction six months later.

Reprinted with permission of the Stowe Reporter

DOCKET 7032
CASE SCHEDULE

02.09.05
Public hearing

02.18.05
Deadline for intervention requests

03.10.05
Site visit

03.18.05
Last date for filing discovery requests on petitioners

03.28.05
Last date for petitioners’ prefiled direct testimony and exhibits

04.11.05
All parties other than petitioners prefile direct testimony and exhibits

05.02.05
Last day to serve discovery on April 11 prefiled testimony and exhibits

05.12.05
Last day for discovery responses

05.23.05
All parties prefile rebuttal testimony and exhibits

06.03.05
Last day to serve discovery on rebuttal prefiled testimony and exhibits

06.13.05
Last day for responses to rebuttal discovery

06.27.05
All parties prefile surrebuttal testimony and exhibits

07.06.05
Technical hearing

07.07.05
Technical hearing

07.08.05
Technical hearing

07.18.05 (week of)
Technical hearings

08.08.05
Briefs due

08.22.05
Reply briefs due

10.19.05
Proposal for decision issued

11.04.05
Comments due on proposal for decision

12.07.05
Oral argument on proposal for decision


BOARD SCHEDULING ORDER (PDF)

SCHEDULE CHANGE MEMO OF 04.14.05 (PDF)