LAMOILLE COUNTY TRANSMISSION UPGRADE PROJECT

Information Resources

VERMONT DEPARTMENT OF PUBLIC SERVICE

05.19.04
Power line through Vt. forest?
Planners wrestle with tough question: where to hide 58-foot, 115 kilovolt towers?

BY SCOTT MONROE, STOWE REPORTER

Stowe town planners and local electric officials on Monday considered an entirely new route for a controversial, high-voltage power line, proposing to run it through the Waterbury State Forest instead of on an existing power-line corridor parallel to Route 100 from Duxbury to Stowe.

The route through the state forest would require a 150-foot right-of-way to accommodate the 58-foot-tall towers and the 115 kilovolt line, and a portion of the line would go through the Town of Bolton.

Stowe planners said they want to consider every possible options to make the proposed line less visible and removed from residential areas.

“We want to look at that, Waterbury State Forest...look at that seriously, and underground,” said Planning Commission Chairman Paul Percy. “We got to know what the costs are.”

The current Route 100-corridor proposal has come up against fierce opposition from both homeowners who are concerned about giving up additional land for right-of-way for the project and others who say the bigger power line will be ugly. Stowe planners, electric department officials and a handful of residents attended the meeting Monday night and discussed a variety of alternatives.

Under the state forest concept the power line would still be visible in Stowe, near where Moscow Road intersects with Route 100. But it would bypass Stowe residential areas such as Black Bear Run where opposition to the proposed line is strong.

Town officials agreed the state forest concept would be difficult for Vermont’s Public Service Board to support, given the potential encroachment on state land and wildlife. As a result town officials discussed other possibilities, such as burying the line or changing the pole designs.

“It seems to me we only have three options: go up, go down, or go elsewhere,” said commission member Scott Noble.

Ideas discussed will be sent to Vermont Electric Power Company officials who have been contracted by local utilities to solve Lamoille County’s growing power needs. VELCO, which devised the original Route 100-corridor proposal, has agreed to review ideas emanating from Stowe town agencies and residents, develop cost estimates and alternative plans.

At the meeting was Bernard Machia, general manager of the Stowe Electric department, which is among the regional utlities seeking the greater electric capacity to meet growing demand. Increased electricity needs and aging infrastructure have led to concerns about the reliability of local electric service, with potential for blackouts and brownouts, Machia and other electric officials have said.

VELCO is proposing to build a 10.5-mile line from Duxbury to Stowe. As proposed, with power lines above ground running on the corridor parallel to Route 100, the line would cost $13.4 million, of which $3 million would be paid by New England utilities. Burying the line or rerouting it would likely cost more.

Both Stowe and Waterbury residents in recent meetings have grilled VELCO on many fronts, including the potential effect of the bigger lines – and a much larger right of way – on property values, aesthetics and health. The proposed line crosses 59 individual properties in Stowe.

Town officials and residents requested more detailed plans and information from VELCO, and the company is working on them.

Members of the Stowe Planning Commission said they want VELCO to discuss as many alternatives as possible to come up with a plan that has the lowest environmental and residential impact.

Burying the high-voltage line in certain areas is one possibility, although the price for those sections would increase by eight to 10 times compared to building the line above the ground.

Another possibility would be to scrap the 58-foot-tall “H” frame power line poles for 61- to 95-foot-tall single steel poles that would carry lines and circuits for both the existing 34.5 kilovolt line and the proposed 115 kilovolt line.

Machia, who has been meeting regularly with local utilities and VELCO officials, advised town planners to come to a consensus as soon as possible, preferably before June 30. That would give enough time for thorough state review and for construction to be completed by November 2006, Machia said.

The November 2006 date is not arbitrary. By the winter of 2006-07 Machia estimates that Stowe Electric Department will need the extra capacity to avoid brownouts and other problems. In addition, Stowe electric stands to save about $350,000 a year in transmission fees on the existing 34.5 kilovolt line unless a new line is built. The fees are currently not fully charged, but they will be imposed beginning in November 2006, Machia said.

Although residents and planners welcomed the news of saving on transmission fees, they had reservations about rushing the project forward.

Stowe resident Steve Riley questioned whether a solution had to be found by November 2006. “Are we really slammed up against the wall?” Riley asked.

“You are,” Machia said. “Cost-wise as well as demand.”

Cady Hill resident Charlie Adams asked if Machia and VELCO are heeding concerns from all homeowners, even those whose land is not in the right-of-way but are affected by the line, including those near the Wilkens Substation.

“I’m looking at 59 landowners... the whole, complete thing through Stowe,” Machia said.

Peter Beddow, a member of the Stowe Development Review Board and resident of Black Bear Run, said the town of Shelburne formed an advisory committee when it deliberated a power line upgrade as part of VELCO’s Northwest Reliability Project. Beddow said he would request at the next Stowe Select Board meeting that a similar committee be formed to raise money for experts and further research to consider burying the line.

“If any place is going to bury a line, I think Stowe should,” Beddow said.

As VELCO develops its plans for permit approval, Stowe planners are hoping to meet with Waterbury’s Planning Commission on June 3, though a time and location has not yet been set.

The Vermont Public Service Board, which reviews Act 248 requests, is the only agency that could reject the proposal or demand changes that are in the “public good.” Local utility companies, which will bond to pay for the project, are currently meeting to devise a cost-sharing formula, in which Stowe is expected to foot about 40 percent. VELCO will take over bond payments after 10 years.

DOCKET 7032
CASE SCHEDULE

02.09.05
Public hearing

02.18.05
Deadline for intervention requests

03.10.05
Site visit

03.18.05
Last date for filing discovery requests on petitioners

03.28.05
Last date for petitioners’ prefiled direct testimony and exhibits

04.11.05
All parties other than petitioners prefile direct testimony and exhibits

05.02.05
Last day to serve discovery on April 11 prefiled testimony and exhibits

05.12.05
Last day for discovery responses

05.23.05
All parties prefile rebuttal testimony and exhibits

06.03.05
Last day to serve discovery on rebuttal prefiled testimony and exhibits

06.13.05
Last day for responses to rebuttal discovery

06.27.05
All parties prefile surrebuttal testimony and exhibits

07.06.05
Technical hearing

07.07.05
Technical hearing

07.08.05
Technical hearing

07.18.05 (week of)
Technical hearings

08.08.05
Briefs due

08.22.05
Reply briefs due

10.19.05
Proposal for decision issued

11.04.05
Comments due on proposal for decision

12.07.05
Oral argument on proposal for decision


BOARD SCHEDULING ORDER (PDF)

SCHEDULE CHANGE MEMO OF 04.14.05 (PDF)