LAMOILLE COUNTY TRANSMISSION UPGRADE PROJECT

Information Resources

VERMONT DEPARTMENT OF PUBLIC SERVICE

07.16.03
Bigger Route 2-Stowe power line eyed
$10-$15 million electric upgrade needed; Stowe to pay portion of system expansion

BY JOHN ZICCONI, STOWE REPORTER

A group of area municipal electric departments is planning to bring a new high voltage power line to Lamoille County that would provide the region with enough electricity to service growth for the next several decades.

Although local power officials cannot say how much excess capacity Lamoille County has left, they acknowledge that additional electric supply is limited. Stowe Mountain Resort, for example, will likely have to pay $1.3 million to upgrade local transmission lines to make the existing system efficient enough to supply adequate power to its proposed ski hamlet at the base of Spruce Peak.

The resort expansion, however, is expected to nearly max out the northern loop, which is the power line that supplies most of Lamoille County and Hardwick. Local electric officials believe an estimated $10 million to $15 million upgrade may be needed to ensure the region has enough power to handle future demand once the new ski village is fully operational.

“Lamoille County is growing,” Bernard Machia, general manager of Stowe Electric, said this week. “We need additional transmission.”

Machia said a consortium of more than a half a dozen electric companies have for months been planning ways to run a 115 kilovolt transmission line from the Duxbury Switching Station on Route 2 to the Wilkins substation along Stowe’s River Road. From Stowe, the new line would feed into the northern loop to supply both Lamoille County and Hardwick.

Currently, the northern loop is fed only by a much smaller, 34.5 kilovolt line. Electric officials hope the new line can be operational by 2006.

Just how much additional power this upgrade would bring, and who would pay for it, is still under review. But once those issues are resolved, Machia said Stowe could likely increase its electrical usage about 30 percent from a peak of 14 megawatts to about 18 megawatts.

“This is something Lamoille County really needs,” said Machia, who is the designated spokesperson for the electric consortium that includes Morrisville Water and Light, Hardwick Electric, Green Mountain Power and others. “We are growing… and it is not all just because of the Mountain Company. We have expansion going on everywhere.”

Chances are the new 115 KV line would use the same right of way as the old 34.5 KV line, which runs through mostly forest land west of Route 100, he said.

Who will foot the bill?
Financing also remains a question. Stowe’s representatives to the Lamoille County Planning Commission have already heard rumblings that Stowe Electric customers will be asked to foot most of the bill.

“The stressing issue as I see it is who is going to pay,” said Lynn Altadonna, a Stowe delegate on the Lamoille County Planning Commission Board of Directors. “One of the notions that was verbalized (at a recent planning commission meeting) is it might be appropriate for Stowe to pay for it since Stowe is responsible for the increase in power.”

Altadonna said the suggestion emanated from representatives of the Vermont Electric Company who gave the Lamoille board its briefing. The local electric consortium has contracted with VELCO to engineer the project.

Stowe paying for the upgrade “was verbalized,” Altadonna said. “But there was not a briefing chart that said let’s stick it to Stowe. It was mentioned as part of the question-and-answer period.”

Financing options for construction vary, but the power companies would likely pass bonds. Bond payment would likely be made through either surcharges or rate increases on electric bills.

Machia called the project’s plans “preliminary,” and said it was too early to know how the improvement would be financed. Final plans would have to be approved by the Vermont Public Service Board, which is the state watchdog agency that looks out for the interest of rate payers, he said.

Asked if Stowe was being viewed as the project’s funding source, Machia said “for the whole thing – no. But I can’t really answer that. We have not done any cost sharing yet. We are just starting to look at that now… We (Stowe) are growing. But we are not the only place growing.”

As for construction, Machia said VELCO is still studying how the 115 KV line could be brought to Stowe. The new line at minimum would require taller poles than the ones currently used to bring power to the region. Whether those polls could also be used to carry the current 34.5 KV line is still being investigated, he said.

But no matter what happens, additional easements from local landowners would likely be necessary, he said.


 

DOCKET 7032
CASE SCHEDULE

02.09.05
Public hearing

02.18.05
Deadline for intervention requests

03.10.05
Site visit

03.18.05
Last date for filing discovery requests on petitioners

03.28.05
Last date for petitioners’ prefiled direct testimony and exhibits

04.11.05
All parties other than petitioners prefile direct testimony and exhibits

05.02.05
Last day to serve discovery on April 11 prefiled testimony and exhibits

05.12.05
Last day for discovery responses

05.23.05
All parties prefile rebuttal testimony and exhibits

06.03.05
Last day to serve discovery on rebuttal prefiled testimony and exhibits

06.13.05
Last day for responses to rebuttal discovery

06.27.05
All parties prefile surrebuttal testimony and exhibits

07.06.05
Technical hearing

07.07.05
Technical hearing

07.08.05
Technical hearing

07.18.05 (week of)
Technical hearings

08.08.05
Briefs due

08.22.05
Reply briefs due

10.19.05
Proposal for decision issued

11.04.05
Comments due on proposal for decision

12.07.05
Oral argument on proposal for decision


BOARD SCHEDULING ORDER (PDF)

SCHEDULE CHANGE MEMO OF 04.14.05 (PDF)